Bid vs. Performance vs. Payment Bonds

A bid bond protects the owner during bidding. A performance bond protects the owner if the contractor does not finish. A payment bond protects subcontractors and suppliers if the contractor does not pay. Public projects usually require all three.

Side-by-side comparison

Bid bondPerformance bondPayment bond
StageBiddingConstructionConstruction
GuaranteesYou will sign and furnish bonds at your priceYou will finish the work under the contractYou will pay subs, laborers, and suppliers
ProtectsProject ownerProject ownerSubs and suppliers, and the owner
Typical amount5% to 10% of bid100% of contract100% of contract
Typical costFree3% of the bond amountUsually included with the performance bond
Ends whenContract and bonds are signedWork is complete and acceptedClaim period ends

The order you will need them in

The bid bond comes first, with your bid. If you win, you sign the contract and provide the performance and payment bonds, which replace the bid bond. If the owner requires a warranty period, a maintenance bond follows at completion.

Why performance and payment bonds come as a pair

Public owners that require one require both. Sureties issue them together, on one application and with a single premium, because the contractor risk behind both is the same.

Which one do I need?

Read the solicitation or contract. It names the bonds, the amounts, and sometimes the form. If you are unsure, send it to us and we will tell you what to apply for.

Common questions

Do I need a bid bond if I do not win?

You provide it with the bid. If you do not win, it is returned or simply expires without a charge claim.

Can one bond cover both performance and payment?

They are separate bonds, but they are usually issued together. Some owners use a combined form.

Which bond protects subcontractors?

The payment bond. It gives unpaid subcontractors, laborers, and suppliers a claim against the surety.